Outline Project Plan for Carpenters WUC (Rev. 7/9/01)
Original Current
Complete test of Set top box capability for receiving video End June Comp. July
Complete test of basic ICA client End August Comp. Aug
Set top boxes delivered End July Est. Sep
Updated ICA client End Nov Est Oct
Produce specification for connecting flatted accommodation and community buildings
End June Comp Jun
Produce specification for connecting houses End Aug Est Dec
Let contract for trenching mid July Comp Aug
Let contract for CAT5 July Comp Aug
Let contract for Core network July Comp Sept (today!)
Let contract for houses Sept Est Jan
CAT 5 wiring in tower blocks completed August Est Nov
CAT 5 wiring in low rise completed August Est Nov
Trenching completed End Aug Est Oct
Core network completed Sept Est Nov
Network to houses completed. Oct Est Mar
Internet feed September Est Oct
Produce specification for network equipment required to deliver required services
July Comp Aug
Equipment installed and tested. August Est Nov
Network equipment review and upgrade January Feb
Software testing with ICA client completed Mid Sept Est Sept
Additional software installation October Est Oct
Testing of DkTV video and web content June (Note 1) Est Oct
Front screens for service complete August (Note 2) Est Nov
DkTV service deployment September (Note 1) Est Nov
Start Here content developed for service N/A Est Oct
Plato software tested and procured N/A Est Sept
Testing of eMail service August Est Nov
Email service deployment September Est Nov
Estate portal developed September Est Oct
Media Trust contract signed Oct Est Oct
SureStart contribution agreed ?
Video on Demand contract achieved N/A Est Jan
Free to air broadcast channels provided N/A Est Jan
DfES contract signed July Est Sept
NN Data Protection Act registration July Est Sept
NN PTO registration (if private owners to be added) Oct Est Dec
NN IP address allocation from RIPE Oct Est Oct
Business Plan for continuation Jan Est Mar
Agreement with College re use of Learn Direct Centre N/A Comp Aug
Employment of workers August Comp Sept
Full project review Feb Est Feb
Information leaflets about service August Est Oct
Estate Conference September Est Jan
Public Launch November? Est Feb
STBs given to initial testers September Est Nov
Deployment to all flatted accommodation October Est Jan
Deployment to houses November Est Mar
In home training starts September Est Nov
Help desk service starts September Est Nov
Cyber Angels estate meetings ?
Estate champions identified July Comp July
Dktv broadcast content will work but interactivity need to be developed for platform.
Given that the system will have a video on demand interface Media Trust participation is now a prior task for this item though a very crude structural mock up has already been created and is at http://www.newham.org.uk/nntv.